Project Details

  Johnson Control Beams

  Location: Port Alegre, Portugal

  Consultants: CME - Lisbon

  Contractor: CME - Lisbon

  Completion Date: January 2002


  Fibrwrap Saturation
 

  Description
: Six concrete beams with corrosion damage required repair and an upgrade to
  accommodate additional loading.

  Problem: The beams supporting the roof of this manufacturing facility had become damaged due
  to corrosion caused by water leaking through the corrugated steel roof. In addition, the existing
  roof was to be replaced with heavier panels.

  Solution: The spalled concrete on the beams was repaired and each beam was brought to its
  original “I” shape. Tyfo® WS was then used to create a radius in the interior corners to receive the
  Tyfo® SCH-35 Carbon System. The exterior corners were brought to a conforming radius by
  means of mechanical grinding. Two layers of Tyfo® SCH-35 were applied with Tyfo®
  FibrAnchors® installed at the terminating ends of each segment.

  Benefits: Using the Tyfo® SCH System, it was possible to complete the repair and upgrade of all
  six beams in four days without any disruption to the operation of the facility.